Homepage  
Search
find:
search for:
   
 
Site Navigation
News / Publications
Jobs
Service
   Add this page to Google Bookmarks
   Add this page to Mister Wong
   Add this page to del.icio.us
 
   Concrete Reinforcing Steel Institute  CRSI / Engineering Data Report\Number 36 - Field Inspection of Rebar  

Field Inspection of Rebar - Page 2

 

 

   c. Independent Testing Laboratory Reports ... The reports on samples taken either at the fabricator's shop or from material shipped to the job site, offer verification of the producer's mill test report.
    d. Approved Placing Drawings ... The latest approved placing drawings should be scheduled to be available for review and study by field placing personnel and the inspector at least one day prior to the actual placing of the rebar.
    e. Material Shipment ... A schedule of anticipated delivery dates should be provided and updated as necessary so that the inspector can schedule his in-place inspection.
   f. Potential Problems ... A discussion between all parties to identify difficult-to-place details, lack of specific details or information on the contract documents, possible structural drawing discrepancy, detailing or placing errors, and verification and acceptability of implemented field changes.
    g. Tolerances ... A discussion with all parties regarding which tolerances are critical, the method of measurement, and the basis for either rejection or acceptance.
    h. Periodic Meetings ... It is recommended that regular scheduled meetings be held in order to discuss the previous inspection reports, any problems that were encountered, solutions to the problems, and the schedule of work for the next period.

MATERIAL INSPECTION
    In-place inspection of rebar starts with the mill test report which in some cases is supplemented by a report from an independent testing laboratory. Both reports should provide data as to grade of steel, tensile properties (yield and ultimate tensile strengths), chemical composition and carbon equivalent (C.E.) in the event the rebar is to be welded, spacing and height of deformations, and ductility (percentage of elongation). The reported data should meet the applicable ASTM standard specified. A visual examination of the mill markings on the bar will identify the material from the producing mill, the type of steel, the grade of steel, and the bar size.

REINFORCING BAR INSPECTION
    Inspection of the rebar installed in the forms is done be visual examination of the layout pattern, by measurement and count. The bar diameter, and if bent, the bar shape can be visually checked. Bar lengths, bar spacing, embedment, bearing on a wall or beam are normally checked by measurement. In a slab, the total number of pieces can be counted with the spacing of the slab bars verified by measurement, all checked against the approved placing drawing in conjunction with the structural drawings. Similarly, beam longitudinals, column verticals, and stirrup and tie spacings are checked.

BAR SUPPORTS
    At the same time beam and slab rebar is inspected, the chair heights should be measured to verify that the concrete cover and clearances will be as specified. It is extremely important that the chairs or standees supporting slab or mat top bars be checked not only for height but also for stability since they can easily be displaces during the placement of concrete. In fact, the entire mat and cages of rebar should be checked for stability for the same reason. Normally side supports are not provided unless called for in the contract documents. If the project specifications require corrosion-protection measures, the class of protection of the bar supports furnished should be verified.

REBAR TYING REQUIREMENTS
    Reinforcing bars are tied together to form a rigid mat for footing, wall, and slab rebar. A rigid cage is formed when beam or column longitudinals are tied to the stirrups and ties. Ironworkers are usually instructed to tie a minimum number of rebar intersections. Unless the project specifications are very specific about the number of intersections to be tied, the inspector should accept the work as done unless it is apparent that the mats or cages of reinforcing steel will be displaced from their inspected position during the casting, screeding, and finishing of the concrete. The placer is responsible for tying bars in such a manner that the rebar will not be displaced. The inspector should only verify and agree that this condition has been achieved. Only coated tie wire should be used to tie coated bars.

SPLICES
    The inspector should pay particular attention to the location and length of lap splices. Lap splices should be specified as to length and location on the contract documents, and in turn shown by length and location on the approved placing drawings. In the event that mechanical splices are required in lieu of lap splices, the placing foreman and/or the mechanical splice supplier should provide the inspector with evidence that the architect or engineer has approved use of the mechanical splice, and provide literature describing the recommended installation procedures.

COATINGS
    A light coating of rust on rebar is not a cause for rejection by the inspector. The ASTM standards describe how to inspect and test rusted rebar. However, dirt, grease, or other deleterious adhesions to the rebar must be removed prior to concrete placement. Tests have indicated that water soluble cutting oils (used when threading ends of bars for attaching to mechanical splices) do not significantly affect bond. If epoxy-coated or galvanized rebar is specified for corrosion protection, the appropriate ASTM standard and the project specifications should be studied to determine the criteria for acceptance or rejection in the event there is damage to the coating. Any corrective actions should follow recommended touch-up procedures and should be completed prior to acceptance by the inspector.

TOLERANCES
    No structure is built exactly level, plumb, straight, and true to line. Tolerances are the means used to establish permissible variations in dimensions and locations. Thus the designer, constructor, and inspector have parameters within which the work can be performed and inspected. Tolerances should neither be overly restrictive nor lenient. The engineer or architect usually specifies the standard tolerances to be followed, normally by reference to the ACI 117 Specification. Judgement on the part of the inspector will establish a range of acceptability. Incompatible tolerances should be referred to the design professional for resolution.

FABRICATING TOLERANCES
    Fabricating tolerances for rebar are tabulated by ACI 117, the ACI Detailing Manual and CRSI's Manual of Standard Practice. Fabricating shops do not have problems meeting the recommended tolerances. Shearing length tolerance for straight bars is plus or minus 1 inch.* Out-to-out dimension of bars with hooks or bends at one end or at both ends is plus or minus 1 inch. Stirrups, hoops, and ties that fit into a beam or column form, bar sizes #3, #4, and #5 [metric bar sizes #10, #13, and #16], with a gross length of 12'-0" or less, have a tolerance of plus or minus 1/2 inch. When a gross length exceeds 12'-0", the tolerance is increased to plus or minus 1 inch.

* 1 inch = 25.4 millimeters.

Request for Information / Request a Catalog from Concrete Reinforcing Steel Institute
 
 
 
To request more information from Concrete Reinforcing Steel Institute, please complete the form below.
 
*Name:    
*Email:    
Company:    
*Company type:    
Phone:    
*Address:    
*Request:    
    (* = Mandatory field) 
Please add me to the mailing list for the free monthly e-Newsletter AECnews.  
     






Printable version Bookmark this page Notify a colleague or friend about this pageHome | Terms of Use | Privacy Statement | Link to AECinfo
AECinfo is a member of Docu Group, the world's largest building products information network.



Copyright © 1996–2008 AECinfo.com