Homepage  
Search
find:
search for:
   
 
Site Navigation
News / Publications
Jobs
Service
   Add this page to Google Bookmarks
   Add this page to Mister Wong
   Add this page to del.icio.us
 
   Concrete Reinforcing Steel Institute  CRSI / Engineering Data Report\Number 38 - Rebar Detailing Placing Drawing And Approvals  

Rebar Detailing Placing Drawing And Approvals - Page 3

 

 

Q14: Why is the CRSI opposed to the requirement that a registered professional engineer seal and sign off placing drawings?
A:
The answers to Questions 7 and 8 state that a detailer is a technically trained person experienced in converting design data into a specific detail format. Requiring a registered professional engineer to seal placing drawings is meaningless and only adds to the cost of detailing without enhancing the product. A detailer does not make engineering decisions. Rather a detailer only determines the quantity, size, length, and bending shapes of bars from specific instructions and data provided by the design drawings and project specifications.

Q15: Can the answer to Question 14 be considered a "POSITION STATEMENT" by the Concrete Reinforcing Steel Institute?
A:
Yes, CRSI does not think that any useful purpose is achieved by the requirement. Aside from the possible ethical and legal violations, the registered professional engineer who sealed a placing drawing would not have been "in responsible charge" and would have little knowledge of the structural analysis and design other than what was shown on the design drawings. The result would be another layer of engineering expense, but certainly not another layer of engineering expertise safeguarding the public.

Q16: What Is CRSI's position regarding the interpretation of building codes?
A:
An experienced detailer can undoubtedly interpret some provisions of a building code, but CRSI believes that code interpretation rightly and properly is the responsibility of the architect/engineer. Only the architect/engineer-of-record, through their structural analysis and the specific design resulting from their analysis, can interpret how the code provisions apply in that particular case.

Q17: When project specifications require submission of placing drawings for review and approval, what does that imply?
A:
An architect/engineer's review implies that the placing drawings have been checked for conformance to the intent of the design drawings and project specifications. For example, in the case of slabs, that the correct bar size and spacing are called out on the placing drawings; and in the case of columns or beams, that the correct bar size and the number of bars are shown. Approval signifies that the placing drawing reflects the structural design.

Q18: What is the fabricator (detailer) responsible for?
A:
The responsibility of the fabricator is to supply all the reinforcing steel requirements shown on the design drawings and project specifications. This means that the fabricator is obligated to furnish the proper number of pieces in the correct bar size, and cut and bent to the correct lengths shown. Should any error occur, such as a quantity shortage, incorrect bar size, wrong bar length, or incorrect bending, the fabricator is obligated to rectify the error expeditiously.

CONCLUSION
Rebar detailing is not a complicated procedure. It is performed by a technician with good skills at interpreting design drawings. Rebar detailing involves the use of information from the design drawings and project specifications to determine the quantity, size, length, and required bending of the reinforcing bars. The detailer then records this information or data on a placing drawing in sufficient descriptive detail so that the field ironworker can place (install) the rebar where intended by the design drawings and project specifications.


CITED REFERENCES

  1. "Quality in the Constructed Project" ASCE Manual No. 73, American Society of Civil Engineers, New York, 149 pp.

  2. "Building Code Requirements for Reinforced Concrete (ACI 318-89) (Revised 1992) and Commentary--318R-89 (Revised 1992)", American Concrete Institute, Detroit, 1992, 347 pp.

  3. Reinforcing Bar Detailer Training Program, Concrete Reinforcing Steel Institute, 1989.

  4. ACI Committee 315, "Details and Detailing of Reinforcement," ACI 315-80(86), in ACI Detailing Manual --1988, SP-66(88), American Concrete Institute, Detroit, 1988, 218 pp.

  5. Reinforcing Bar Detailing, Third Edition, Concrete Reinforcing Steel Institute, 1988, 256 pp.

OTHER REFERENCES

"Reinforced Concrete Design Includes Approval. of Details", ACI Concrete International, V. 10, No. 1, Jan. 1988, pp. 21-22; also CRSI Engineering Data Report No. 28, Reinforced Concrete Design Includes Approval of Details.

Placing Drawings for Reinforcing Steel-Obligations/Responsibilities, Engineering Data Report No. 20, Concrete Reinforcing Steel Institute.

D. P. Gustafson, "Designing and Specifying Rebar Embedments and Splices: Who is Responsible?", ACI Concrete International, V. 14, No. 5, May 1992, pp. 49-50.

*Request for Information / Request a Catalog
 
 
 
To request more information from Concrete Reinforcing Steel Institute, please complete the form below.
 
*Name:    
*Email:    
Company:    
*Company type:    
Phone:    
*Address:    
*Request:    
    (* = Mandatory field) 
Please add me to the mailing list for the free monthly e-Newsletter AECnews.  
     






Printable version Bookmark this page Notify a colleague or friend about this pageHome | Terms of Use | Privacy Statement | Link to AECinfo
AECinfo is a member of Docu Group, the world's largest building products information network.



Copyright © 1996–2008 AECinfo.com