Homepage  
Search
find:
search for:
   
 
Site Navigation
News / Publications
Jobs
Service
   Add this page to Google Bookmarks
   Add this page to Mister Wong
   Add this page to del.icio.us
 
   Concrete Reinforcing Steel Institute  CRSI / Engineering Data Report\Number 39 - Reinforced Masonry  

Reinforced Masonry - Page 2

 

 

Q8: What are the primary building codes covering masonry construction?
A:
"Building Code Requirements for Masonry (ACI 530.1-92/ASCE 6-92/TMS 402-92)" by the American Concrete Institute, American Society of Civil Engineers and The Masonry Society; and the Uniform Building Code. The ACI-ASCE-TMS masonry code is referenced in the BOCA National Building Code and Standard Building Code.

Q9: Who publishes specifications and design guides for masonry construction?
A:
ACI, ASCE and TMS have issued "Specifications for Masonry Structures (ACI 530.1-92/ASCE 6-92/TMS 602-92)", which is an integral part of the building code cited in the Answer to Question 8. Two comprehensive design publications were recently issued: Masonry Designers' Guide by TMS and ACI; and Concrete Masonry Design Tables by the National Concrete Masonry Association (NCMA). The Brick Institute of America (BIA), the Masonry Institute of America (MIA), NCMA, and the Portland Cement Association (PCA) publish a variety of technical information. Some of their publications are listed in the References.

Q10: Do masonry walls require reinforcing steel?
A:
The building code governing the location where the structure is to be built usually will have minimum requirements for "reinforcement". For non-seismic, non-load bearing conditions the usual minimum is horizontal ladder or truss type joint reinforcement spaced 24 in. vertically, and a horizontal bond beam with 144 rebar at each floor level. Vertical rebar may be required depending on the clear story height of the wall.

Q11: What is a "fully reinforced" masonry wall?
A:
A fully reinforced wall is one designed to resist both dead and live vertical loads (load bearing wall) plus lateral loads due to either wind or seismic forces. The codes then require rebar in both directions. For instance in Seismic Zones 3 and 4, the minimum horizontal and vertical reinforcement is #4 rebar spaced 48 in. on center, 144 at the base and top of wall, 144 at all floor levels, and 1-#4 jamb, sill, and head bars at openings. Lateral load requirements will usually govern the amount of rebar required, normally much more than the code minimums.

Q12: Is rebar the only reinforcing steel used in masonry?
A:
No, steel wire manufactured in a ladder or truss configuration, or expanded metal lath, is placed in the 3/8-in. horizontal mortar joint, whereas rebar is within fully grouted cells or fully grouted bond beam units. Special truss or ladder configurations, wire ties, or metal straps are also used to hold a multi-wythe wall together.

Q13: How is masonry reinforcing (rebar) furnished to the jobsite?
A:
In a similar manner as the rebar for cast-in place concrete, that is, by means of a supply contract between the fabricator and either the general contractor or the masonry subcontractor. The contract should be specific with regard to the requirements for detailing, that is, it should spell out whether open or closed end block is specified, whether high- lift or low-lift grouting techniques will be used, and whether or not complete placing drawings are to be furnished.

Q14: How are masonry walls detailed?
A:
Detailing procedures vary from region to region, but in general, masonry walls are detailed in a similar manner as concrete walls (refer to Question 13). Figure 11 illustrates a placing drawing for a masonry wall in a seismic zone using open end block and high-lift grouting techniques. Figure 12 illustrates a placing drawing for a masonry wall constructed with closed end block and low-lift grouting procedure. However, it must be noted that some masonry contractors purchase the rebar in stock lengths, preferring to cut and place the rebar as the mason lays up the CMU.

Q15: What is meant by "low-lift" and "high lift" grouting?
A:
These terms are decreasing in use as both designers and contractors realize the practical and economical feasibility of building masonry walls in floor height (or higher) increments. Generally, "low-lift" procedures limited the height of laid-up CMU to 4 feet, but it is hard to envision how a cavity of that height can be cleaned without a clean-out opening. "High-lift" grouting requires a cleanout opening of sufficient size to remove mortar drippings and other debris at the bottom of all cavities to be grouted. Fluid consistency grout is placed in all cavities with reinforcing bars and any other cells required to be grouted, and then consolidated with a vibrator. Generally, grout is placed in successive 4-foot lifts to allow better consolidation procedures.

*Request for Information / Request a Catalog
 
 
 
To request more information from Concrete Reinforcing Steel Institute, please complete the form below.
 
*Name:    
*Email:    
Company:    
*Company type:    
Phone:    
*Address:    
*Request:    
    (* = Mandatory field) 
Please add me to the mailing list for the free monthly e-Newsletter AECnews.  
     






Printable version Bookmark this page Notify a colleague or friend about this pageHome | Terms of Use | Privacy Statement | Link to AECinfo
AECinfo is a member of Docu Group, the world's largest building products information network.



Copyright © 1996–2008 AECinfo.com