Homepage  
Search
find:
search for:
   
 
Site Navigation
News / Publications
Jobs
Service
   Add this page to Google Bookmarks
   Add this page to Mister Wong
   Add this page to del.icio.us
 
   Concrete Reinforcing Steel Institute  CRSI / Engineering Data Report\Number 40 - Construction Tolerance Conflicts in Reinforced Concrete  

Construction Tolerance Conflicts in Reinforced Concrete - Page 2

 

 


MIN. ALLOWED COVER = 1 1/2"- 1/2" = 1"
ACTUAL COVER = 5/8" < 1" MIN.

Fig. 1 Beam Stirrup Cover

Formwork And Member Profile
    Widely used concrete joist construction is formed with thin gage inverted "U" shaped metal forms which lap at joints and have flanges which are nailed to framing material forming the joist soffit. The lap joints and soffit connection typically have offsets of up to 1/2 in. with occasional 1 in. offsets (Figure 3). While not meeting the ACI cross-section tolerance of -1/4 in., +3/8 in. for members up to 12 in. in width, the offsets do meet ACI 117 Class C (1/2 in.) and Class D (1 in.) tolerances for offsets between adjacent pieces of formwork. Fortunately, the offsets usually either make the member thicker or do not occur at locations which would affect the structural integrity of the concrete joist. The end 3 to 6 ft of the joist rib is structurally most vulnerable to thickness deficiency.
    This conflict can best be resolved by recognizing that the tolerance range required with this method of construction is greater than with more costly alternatives. Class "C" or "D" tolerances should be specified and, except in areas affecting structural integrity, the cross-sectional tolerances should not be strictly applied to this type of construction.

Conflicts Between Members
    In a long span beam and slab parking structure, the floor-to-floor height is often 10 ft 0 in. with a 3-ft deep beam. The minimum clearance specified is 7 ft 0 in. which leaves zero tolerance. The ACI tolerances on the forming would allow +/- in. for the soffit and top elevation. This could reduce the clearance by 1-1/2 in.
    The problem worsens in the ramp areas, Figure 4, where the slope of the ramp at 5 or 6 percent grade makes the clearance on the uphill side of the beam 3/8 in. less than at the centerline. This occurs because the beam soffits are placed level rather than parallel to the slope of the ramp.


FOR DEPTH A, STIRRUP HEIGHT = 26 3/8"
FOR DEPTH B, STIRRUP HEIGHT = 27"

Fig. 2 Measuring Beam Depth

    Deciding where the beam depth is to be measured presents a third problem on sloping or ramped surfaces. If the beam depth is measured on the downhill side, the soffit of the beam is lowered by 3/8 in. which reduces the clearance by 3/8 in.
    The simultaneous occurrence of these three conditions is quite normal. What was intended to be 7-ft clear becomes 6 ft 9-3/4 in. This is 2-1/4 in. less than planned. The story height should be increased by 2-1/4 in. to allow for the construction tolerances.
    The use of post-tensioning sometimes compounds the problems of trying to keep the edge of the building within acceptable tolerance (Figure 5). The usual procedure would be to cast the first lift columns, then cast the floor slab. Before tensioning the floor beams and slabs, it is likely that the 2nd lift of columns has been cast. The tensioning operation compresses the concrete and tends to pull the edges of the building toward the center or other stable location. The result may be the movement of the slab by as much as 3/4 in., pulling the first floor columns out of plumb and moving the 2nd lift of columns laterally by this amount. The casting of the 2nd slab and the 3rd lift of columns followed by the tensioning of the 2nd floor system moves the top of the 2nd lift of columns an additional 3/4 in. inward for a total movement of 1-1/2 in. As the building progresses, the offsets progress. A 10-story building could be off by as much as 7-1/2 in. unless corrective measures were taken.
    The common remedy is to anticipate the movement and lean the columns outward and build the slab edge beyond its desired location. Unfortunately, the movement does not always occur due to the level of the post-tensioning force or constraints in the building geometry. This is a condition where the Architect/Engineer should advise the Contractor of the anticipated movement so the Contractor can act accordingly.

Request for Information / Request a Catalog from Concrete Reinforcing Steel Institute
 
 
 
To request more information from Concrete Reinforcing Steel Institute, please complete the form below.
 
*Name:    
*Email:    
Company:    
*Company type:    
Phone:    
*Address:    
*Request:    
    (* = Mandatory field) 
Please add me to the mailing list for the free monthly e-Newsletter AECnews.  
     






Printable version Bookmark this page Notify a colleague or friend about this pageHome | Terms of Use | Privacy Statement | Link to AECinfo
AECinfo is a member of Docu Group, the world's largest building products information network.



Copyright © 1996–2008 AECinfo.com