general construction data
Illustrated, step-by-step instructions are given in
Homasote Bulletin FD-8-222-5 which details
construction requirements and Homasote approved
installation procedure. The following information is
intended only for product evaluation.
Construction Site Storage - Protect Floor Decking, as
any valuable building product, by storing on a dry
platform under shelter. Keep wrapped in
weather-capped shipping units until ready to use. If no
shelter is available, stack units on skids, 8 " above
grade. Panels must be installed in a dry condition. Every
effort should be made to prevent water ponding on
exposed floor decking.
Framing - Use cross bridging to secure floor joists.
Solid bridging is not recommended. Ends of Floor
Decking must bear on solid framing without breaks and
at all points where framing changes direction. Wall and
partition plates can be applied directly over Floor
Decking, across floor joists. If partition parallels floor
joists, adequate support framing must be installed under
partition plate.
Installation - Homasote 4-Way® Floor Decking must
be installed to accommodate expansion and contraction.
In large area platforms, provide 1/2" gap for every 50' of
length. Trim ends if necessary to assure support.
Provide 1/2"' gap at all abutting masonry walls. Stagger
end joints on alternate joists. Do not butt squared ends
tightly. Gap 1/16" to 1/8 ". Snug all T&G edges together
tightly.
Adhesive is recommended with annular threaded nails in
application of Floor Decking to effectively cut noise
transmission through nails and to provide a stronger,
squeak resistant floor.
Glue-nail method - Apply continuous 3/8" beads of
APA approved decking adhesive to enough framing for
installing one or two panels at a time. Apply two parallel
beads to joists supporting butt joints. Apply a continuous
bead into groove of Floor Decking T&G.
Position panel and drive three (for 2' wide panels) or
five (for 4' wide panels) Homasote #3190 nails (3" long,
3/8" dia. head, annular threaded) into centers of each
joist, starting at mid-panel and nailing out to ends. Keep
nails back 3/4" from ends, toenailing if required.
Nail each Floor Decking panel completely before
proceeding to the next.
Complete nailing of the panels within the glue
manufacturer's specified time limit.
All nails must be dimpled 1/16 " below surface. |