7510 Guide Specifications:

Asphalt, Gravel Surfaced, Built-Up Roof System

F. Cants

1. Perlite Cant and Tapered Edge Strips: Perlite (Fes-Cant Plus) boards, fire resistant, preformed to 45 degree (0.79 rad.) angle; Tapered Fesco Edge Strip.

G. Accessories

1. Roofing Nails: 1 inch (25 mm) square or round head, ring shanked galvanized or non-ferrous type, length as required to suit application.

2. Traffic Pads: JM DynaTred.

3. Insulation Fasteners: Premium No. 12 hexhead fastener coated for superior corrosion resistance. JM UltraFast with UltraFast Locking Plastic Plates or UltraFast Galvalume Metal Plates.

4. Prefabricated Expansion Joint Covers: EPDM sheet attatched to sheet metal flanges with bifurcated crimp, with a closed cell polyethylene foam backer; JM Expand-O-Flash.

5. Roof Drains: Drain having an integral, flexible Neoprene bellows and the drain body composed of PPO engineering resin. Drain capable of accomodating 1" (25 mm) movement in all directions; JM Flex-I-Drain.

6. [Roof Vents: Molded polyethylene body with one-way silicone rubber valve; JM FP-10 One Way Roof Vent.]

7. [Roof Fascia: Factory-made fascia system, consisting of [0.050" (1.3 mm) aluminum] [24 ga. (0.6 mm) galvanized steel] cover plate, waterdam, and concealed cover plate; JM Presto Lock.]

III. EXECUTION

A. Examination

1. Verify that surfaces and site conditions are ready to receive work.

2. Verify that deck is supported and secured.

3. Verify that deck is clean and smooth, free of depressions, irregularities, or projections, properly sloped to [drains][,][.] [valleys][,][.] [or] [eaves.]

4. [Verify that adjacent pre-cast concrete roof members do not vary more than 1/4 inch (6 mm) in height.] [Verify grout keys are filled flush.]

5. Verify that deck surfaces are dry and free of dirt and debris. [Verify flutes of metal deck are clean and dry.] Confirm dry deck by moisture meter with [12] [_____] percent moisture maximum.

6. Verify that roof openings, curbs, pipes, sleeves, ducts, and vents through roof are solidly set, and [wood cant strips] [wood nailing strips] [and reglets] are in place.

7. Start of work means installer accepts existing [surfaces.] [substrate.]

B. Protection

1. Protect building surfaces against damage from roofing work.

C. Preparation – Wood Deck

1. Verify flatness and joint openings of wood decking. [Fill knot holes with latex filler.] [Cover holes with sheet metal.]

D. Preparation – Concrete Deck

1. Fill surface honeycomb and variations with latex filler.

E. Preparation – Metal Deck

1. Verify that all units are properly secured in place.

2. [Install preformed sound absorbing glass fiber insulation strips supplied by Section 05311 in acoustic deck flutes. Install in accordance with manufacturer’s instructions.]

Request for Information / Request a Catalog from Johns Manville
 
 
 
To request more information from Johns Manville, please complete the form below.
 
*Name:    
*Email:    
Company:    
*Company type:    
Phone:    
*Address:    
*Request:    
    (* = Mandatory field) 
Please add me to the mailing list for the free monthly e-Newsletter AECnews.  
     






Printable version Bookmark this page Notify a colleague or friend about this pageHome | Terms of Use | Privacy Statement | Link to AECinfo
AECinfo is a member of Docu Group, the world's largest building products information network.



Copyright © 1996–2008 AECinfo.com