Homepage  
Search
find:
search for:
   
 
Site Navigation
News / Publications
Jobs
Service
   Add this page to Google Bookmarks
   Add this page to Mister Wong
   Add this page to del.icio.us
 
   Johns Manville  Commerical Industrial Roofing Systems\APP Modified Bitumen  

APP Bitumen Modified - Page 5

 

 

jmlogo.jpg (11366 bytes)

APP Modified Bitumen Specifications


 

7B.12.11 Nailable and Lightweight Concrete Decks: On decks with a slope over 1/2 " per foot (41.6 mm/m), the roofing felts must be installed parallel to the incline. Nail the end laps of the modified bitumen cap sheet across the width of the sheet on 8 1/2 " (216 mm) centers. All nails are to be covered by the lap of the next sheet. For slopes from  1/2 " to 2" per foot (41.6 to 167 mm/m), a full-length sheet can be used. For slopes from 2" to 3" per foot (167 to 250 mm/m), a half-length sheet should be used.

7B.13 Phase Construction

7B.13.1 One of the greatest hazards of roof construction is the application of a roofing system in "phases", where a partially completed roof system is left exposed to the weather overnight or longer. This can lead to entrapped moisture which can cause premature failure of the membrane.

7B.13.2 When the installation of the cap sheet is delayed for any reason, the following procedures should be followed:

A.

Prior to the application of the modified bitumen cap sheet, the surface of the membrane must be examined thoroughly for the presence of any moisture. If moisture is present, the application of the cap sheet is not to proceed until the moisture has been removed or evaporated and the surface is dry.

B.

The surface of the membrane must be properly cleaned and primed if contaminated by dirt, dust, or debris. The primer must be completely dry prior to installation of the modified bitumen cap sheet.

7B.13.3 Under no circumstances shall the installation of the modified bitumen cap sheet be delayed more than 5 days after completion of the intermediate plies of the roofing system.

7B.13.4 Only multiple felt (two felts with modified cap sheet) should be considered for the delay in application of the modified bitumen cap sheet. Single ply felt or base felt systems must receive the modified bitumen cap sheet on the same day.

7B.14 Cold Weather Application

7B.14.1 APP and PAO modified bitumens require special application techniques when they are being installed in cold weather. The following precautions shall be taken when the ambient temperature drops below 50°F (10°C), and are mandatory below 40°F (4°C):

A.

Modified bitumen products shall be kept warm, or warmed prior to installation. Store these materials indoors or in heated storage units or warming boxes. If these facilities are not available, placing the materials in direct sunlight may help.  Make certain that modified bitumen rolls are stored on end only; do not store rolls on their side.

B.

When the conditions are extreme (below 40°F [4°C]), the rolls must be heated or completely unwound and allowed to warm on the roof for 15 to 20 minutes. This shall be done with the darker side of the sheet up. The sheet may then be installed using conventional application techniques.

C.

When the ambient temperature is below 40°F (4°C), extra care must be used when handling and storing APP and PAO modified products. During cold weather, these modified bitumen products must be stored on end in a heated trailer or building, and only the rolls needed for immediate application should be outside. Materials must be kept dry. Never throw or drop rolls of modified bitumen products during cold weather. Sudden shocks can cause cracking of the asphalt. DO NOT DOUBLE STACK (with or without pallets). For heat-weld applied products, heat the substrate prior to rolling the molten modified bitumen into place. Special attention should be given to the lap area so proper adhesion can be obtained.

7B.15 Temporary Roof Coverings

7B.15.1 At times, an owner or general contractor may require the building to be closed in at a time when the weather is not conducive to good roof construction, or the roof area may have to be used as a work platform during construction. Historically, this situation has led to phase construction, which has resulted in premature roof failure.

7B.15.2 When the complete roof cannot be installed in one operation, the following procedures are recommended:

A. Nailable Decks:

1. Apply one layer of an approved JM base felt, lapping the felt 2" (51 mm), and nailing 9" (229 mm) o.c. along the lap and 12" (305 mm) o.c. through the center of the sheet. (Sheathing paper should first be installed on wood board decks.)

*Request for Information / Request a Catalog
 
 
 
To request more information from Johns Manville, please complete the form below.
 
*Name:    
*Email:    
Company:    
*Company type:    
Phone:    
*Address:    
*Request:    
    (* = Mandatory field) 
Please add me to the mailing list for the free monthly e-Newsletter AECnews.  
     






Printable version Bookmark this page Notify a colleague or friend about this pageHome | Terms of Use | Privacy Statement | Link to AECinfo
AECinfo is a member of Docu Group, the world's largest building products information network.



Copyright © 1996–2008 AECinfo.com