Homepage  
Search
find:
search for:
   
 
Site Navigation
News / Publications
Jobs
Service
   Add this page to Google Bookmarks
   Add this page to Mister Wong
   Add this page to del.icio.us
 
   Schindler Elevator Corp.  Traction Elevator  

Traction Elevator - Page 37

 

 

zsch109a.jpg (6952 bytes) General Requirements

Requirements for installation vary by type of equipment selected. These general requirements will serve as a guide to assist you in preparing your building for the installation of Schindler elevators.

All designs, clearances, construction, work-manship and materials, unless specifically excepted, shall be in accordance with the requirements of the ASME A17.1 or CAN/CSA-B44 Code plus applicable Building Code. For specific rules, refer to ASME A17.1 Parts I and II or CAN/CSA-B44 Sections 1, 2 and 3 for traction elevators. Local requirements must be used if more stringent.

Items To Be Provided

To complete the installation, the following items must be considered, which are not included in the elevator contract:

Hoistway

1. Clear, plumb hoistway, with variations not to exceed 1" (25mm) at any point. Two-hour fire resistance rating of hoistway walls or rating to meet applicable local codes.

2. 750 bevel guards on all projections, recesses or setbacks over 2" (51mm) ASME A17.1 or 100mm CAN/CSA-B44 except on side used for loading or unloading.

3. Number of cars in hoistway, minimum size of cars, venting and fire rating of doors and entrances must be specified per applicable Building Code.

4. Maximum allowable vertical spacing of rail supports to be 16' (4877mm). Divider beams between hoistway at each floor, and under machine room floor, for guide rail bracket supports.

5. Lighting for each elevator machine room, as indicated by elevator contractor.

6. Recesses, support and patching, as required to accommodate hall button boxes, signal fixtures, etc.

7. All barricades either outside elevator hoistways or between elevators inside hoistways as required.

8. Dry pit reinforced to sustain normal vertical forces from rails and buffers. Consult Schindler sales representative for rail forces and buffer impacts. Where there is space below the pit floor which can be occupied, a counterweight safety is required. Consult your elevator contractor for incremental hoistway dimensions.Buffer inspection ladders and platforms if required.

9. Convenience outlet and light fixture in pit with switch located adjacent to access door per ASME A17.1 Rule 1061e and CAN/CSA-B44 2.7.5.

10. Where access to pit is by means of lowest hoistway entrance, vertical ladder of non-combustible material extending 42" (1070mm) minimum above sill of access door or handgrips shall be provided to the same height.

11. Entrance wall and finished floor are not to be constructed until after door frames and sills are in place.

    a. where front walls are of reinforced concrete, the concrete openings must be minimum 12" (300mm) wider than the outside trim of door frames and 6" (150mm) higher than head trim.

    b. Where drywall or sheet rock construction is used for front walls, it shall be of sufficient strength to maintain the doors in true lateral alignment. Drywall contractor to coordinate with the elevator contractor. Note : A support member (spreader beam) must be provided for floor heights greater than 12'-0" (3658mm) to support entrance header struts.

    c. Door frames are to be anchored to walls and properly grouted in place to maintain legal fire rating (masonry construction).

12. Furnishing, installing and maintaining the required fire rating of elevator hoistway walls, including the penetration of fire wall by elevator fixture boxes, is not the responsibility of the elevator contractor.

13.    The interface of the elevator wall with the hoistway entrance assembly shall be in strict compliance with the elevator contractor's requirements.

14. For applications requiring grouted sills, provide sill supports with 21/2"x4" (65mm x 102 mm) minimum floor recess the full width of the hoistway. Grout full length and width after sills are set.

15. When sill angles are provided by the elevator manufacturer, hoistway should be capable of accepting stud type fasteners and supporting loads imposed based on loading of elevator.

Machine Room

16. Enclosed and protected machine room.

17.    Access to machine room and machinery space as required by governing code or authority.

18. Lighting, convenience outlets, heating, cooling and ventilation of machine room and machinery space. Machine room temperature to be maintained between 55° F and 90° F (13° C and 32° C). Relative humidity to be maintained at 95% or less non-condensing.

19.   A fused disconnect switch for each elevator and light switch located per National Electrical Code, (NFPA No. 70), and where practicable, located inside machine room adjacent to door.

20. Suitable copper feeder, ground and branch wiring circuits for signal system and power operated door, including main line switch. Feeder and branch wiring circuits for car light and fan, including main line switch. Ground fault protection as required by NEC 620-85.

21. Reinforce concrete machine room floor slab or grating, as specified, which must not be placed over the hoistway until elevator machinery is set in position.

22. Hoisting beams, trap doors, ladders or stairs and other means of access to machine room of maintenance and equipment removal purposes.

23. Supports for machine and sheave beams including wall pockets and patching after beams are set in place. Beams for machine and sheave will be mounted on top of building supports. Consult elevator contractor and elevator shop drawings for overhead reactions and elevation of supports.

24. Convenience outlet and telephone outlet on control panel.

25. All conduit and wire runs remote from either the machine room or the hoistways.

26. Heat, smoke or products of combustion sensing devices connected to elevator machine room terminals when such devices are required.

27.    Architectural precautionary measures to provide sufficient attenuation for rooms near the machine room in which air borne noise produced by the elevator system would be inconvenient.

Emergency Provisions

28. Elevator Firefighter's Service is required per ASME A17.1 Rule 211.3 and may be required per CAN/CSA-B44 3.12.15.1.1. Elevator Firefighter's Service wiring and inter-connections to automatic sprinkler systems or heat and smoke sensing devices furnished by others. Emergency services may be required by Building Code.

29. When emergency/standby power operation of elevators is required, the Electrical Contractor should coordinate with your elevator contractor for operation requirements.

30. Provisions for earthquake protection, dictated by the Building Codes, may be required. Consult your elevator contractor special requirements.

zsch109b.jpg (8119 bytes)

U.S. Headquarters
Schindler Elevator Corporation
20 Whippany Road, P.O. Box 1935
Morristown, New Jersey 07962-1935
(973) 397-6500
Canada Headquarters
Schindler Elevator Corporation
40 Cowdray Court
Scarborough, Ontario M1S 1A1
(416) 332-8280

Visit Our Web Site: www.us.schindler.com

Request for Information / Request a Catalog from Schindler Elevator Corp.
 
 
 
To request more information from Schindler Elevator Corp., please complete the form below.
 
*Name:    
*Email:    
Company:    
*Company type:    
Phone:    
*Address:    
*Request:    
    (* = Mandatory field) 
Please add me to the mailing list for the free monthly e-Newsletter AECnews.  
     






Printable version Bookmark this page Notify a colleague or friend about this pageHome | Terms of Use | Privacy Statement | Link to AECinfo
AECinfo is a member of Docu Group, the world's largest building products information network.



Copyright © 1996–2008 AECinfo.com